Navoi combined cycle thermal power plant with a capacity of 650 MW

Projects Description

Navoi combined cycle thermal power plant with a capacity of 650 MW

Construction Work:

  • 63,000 m³ Concrete Work
  • 78,000 m² Formwork Installation
  • 12,000 tons Reinforcement Fabrication and Installation
  • 64,000 m² Installation Work

 

Metal Work:

  • 4,000 tons Metal Structure Fabrication and Installation
  • 88 tons Galvanized Steel Work – Material Supply

 

Contractor Type:

  • Subcontractor

 

Partner company:

  • CALIK ENERJI & MITSUBISHI CORPORATION

Projects Details